Question: Select the best answer for the multiple choice or True/False (T/F) questions: 1. Which of the following is not one of the classifications for assessing
Select the best answer for the multiple choice or True/False (T/F) questions: 1. Which of the following is not one of the classifications for assessing a project portfolio?
A. Pearls
B. Bread-and-butter
C. Multi-weight scoring
D. Oysters E. White elephants
2. A major project proposal form will likely include all of the following except:
A. Project Name
B. Major deliverables of the project
C. The financial source D. Goal Schedule and team task assignments
E. All of these are likely to be included