Question: Select the item below that would be reviewed at the transfer meeting. Project budget and timeline Stakeholders' expectations Risks related to the project deliverables Governance

Select the item below that would be reviewed at the transfer meeting.
Project budget and timeline
Stakeholders' expectations
Risks related to the project deliverables
Governance for implementing deliverables