Question: Select the ONE INCORRECT statement about a Risk Assessment Worksheet. Group of answer choices A. This worksheet identifies the mitigation strategies and the contingency plans
Select the ONE INCORRECT statement about a "Risk Assessment Worksheet." Group of answer choices A. This worksheet identifies the mitigation strategies and the contingency plans for managing the risk. B. This worksheet includes a "risk category" to help in categorizing this risk along with all of the other risks the project manager is managing. C. This worksheet contains a "timeline" of when the risk may occur to help with prioritizing this risk along with all of the other risks the project manager is managing. D. This worksheet lists the risk owner who should be the same person that identifies the risk. E. This worksheet is created to identify a single risk.