Question: Select the statements below that reflect updating progress using the % complete with earned value (there may be more than one correct answer) A. A
Select the statements below that reflect updating progress using the % complete with earned value (there may be more than one correct answer)
A. A credit is applied to the activity once the activity starts
B. A % complete should be based on the duration or costs
C. earned value is an estimate of the value of the work completed
D. The project manager should set guidelines on how to report the earned value of the work completed