Question: Select which construction delivery method best fits the following description. In this construction delivery method, the owner contracts separately with the design team and the
Select which construction delivery method best fits the following description. In this construction delivery method, the owner contracts separately with the design team and the contractor, or construction manager, who will work on the owner's behalf. This is system is also referred to as negotiated work because the construction manager negotiates a fee for management services with the owner. Early in the design process, the construction manager is required to guarantee that the total construction cost will not exceed a guaranteed maximum price (GMP). Group of answer choices design-build construction management-at-risk integrated project delivery design-bid-build