Question: Send to expert. Section 9 . 6 , Problem # 3 3 . Planned order releases ( POR ) for three components, A , B

Send to expert. Section 9.6, Problem #33. Planned order releases (POR) for three components, A, B, and C, are given below. Suppose that the
yields for these components are respectively 84 percent, 92 percent, and 70 percent. Assuming lot-for-lot scheduling, how should
these be planned order releases be adjusted to account for the fact that the yields are less than 100 percent?