Question: Sequence Job 1 A 2 B 3 C 4 D Part 5 The average tardiness ( job lateness ) for the sequence developed using the

Sequence
Job
1
A
2
B
3
C
4
D
Part 5
The average tardiness(job lateness) for the sequence developed using the FCFS rule=
6.50 days (round your response to two decimal places).
Part 6
The average completion time(flow time) for the sequence developed using the FCFS rule=
11.75 days (round your response to two decimal places).
Part 7
The percentage utilization for the sequence developed using the FCFS rule=
42.55%(enter your response as a percentage rounded to two decimal places).
Part 8
b) Using the SPT(shortest processing time) decision rule for sequencing the jobs, the order is(to resolve a tie, use the order in which the jobs were received):
Part 9Part 10Part 11
Sequence
Job
1
B
2
C
3
A
4
D
Part 12
The average tardiness(job lateness) for the sequence developed using the SPT rule=
5.00 days (round your response to two decimal places).
Part 13
The average completion time(flow time) for the sequence developed using the SPT rule=
18 days (round your response to two decimal places).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock