Question: Sequence the following according to the Shortest Process Time (SPT) rule, and then compute the Flow Times, the average flow time, as well as the

Sequence the following according to the Shortest Process Time (SPT) rule, and then compute the Flow Times, the average flow time, as well as the Delay Times, and the average delays times, for all the jobs in that sequence:

Jobs --> A B C D E

Process Time 6 2 4 1 5

Due Date 16 7 14 8 9