Question: Suppose for a given set of tasks, the average flow time per job according to the critical ratio sequence is 50 days. What is the
Suppose for a given set of tasks, the average flow time per job according to the critical ratio sequence is 50 days. What is the possible average flow time per job if we prioritize the tasks according to the shortest processing time (SPT) rule? Write your choice in the box on the left. A. 45 days B. 55 days C. 65 days D. 75 days E. Given information is insufficient to answer this question