Question: Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. ( i . e .

Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. (i.e.- When a job is complete on its first workstation, it must wait 1 hour (move time) before it begins on the next station)
Example of Move Time
Machine A
1
1
1
Machine B
1 hr move time
1
1
1
1
1
Sequence the jobs in priority order 1,2,3,4. Assume 8hr work days.
Job
Work Center/Machine Hours
Due Date (Days)
1
A/3, B/2, C/2
3
2
C/2, A/4
2
3
B/6, A/1, C/3
4
4
C/4, A/1, B/2
3