Question: Sequencing [WLOs: 2] [CLOs: 1, 3, 5] Using the information presented in the following table, identify the processing sequence that would result using (a) first
Sequencing
[WLOs: 2] [CLOs: 1, 3, 5]
Using the information presented in the following table, identify the processing sequence that would result using (a) first come, first served (FCFS), (b) shortest processing time (SPT), (c) earliest due date (EDD), and (d) critical ratio (CR). For each method, determine (a) average job flow time, (b) average job tardiness, and (c) average number of jobs in the system. Jobs are listed in order of arrival. (Hint: First determine the total job time for each job by computing the total processing time for the job and then adding in the setup time. All times and due dates are in hours.)
| Job | Processing Time per Unit | Units per Job | Setup Time | Due Date |
| a | .14 | 45 | 0.7 | 4 |
| b | .25 | 14 | 0.5 | 10 |
| c | .10 | 18 | 0.2 | 12 |
| d | .25 | 40 | 1.0 | 20 |
| e | .10 | 75 | 0.5 | 15 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts