Question: Set the following problem and solve for the minimum cost plan. Period Feb Mar Apr Demand 55 70 75 Capacity Regular 50 50 50 Overtime
Set the following problem and solve for the minimum cost plan.
|
| Period | ||
|
| Feb | Mar | Apr |
| Demand | 55 | 70 | 75 |
| Capacity |
|
|
|
| Regular | 50 | 50 | 50 |
| Overtime | 5 | 5 | 5 |
| Subcontract | 12 | 12 | 10 |
| Beginning Inventory | 10 |
|
|
| Costs |
|
|
|
| Regular time | $60 per unit | ||
| Overtime | $80 per unit | ||
| Subcontract | $90 per unit | ||
| Inventory carrying cost | $1 per unit per month | ||
| Back order cost | $3 per unit per month | ||
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts