Question: Set up and solve an LP model using Excel to crash this project to 24 days. What is the total crashing cost? ACTIVITY IMMEDIATE PREDECESSORS
Set up and solve an LP model using Excel to crash this project to 24 days. What is the total crashing cost?
| ACTIVITY | IMMEDIATE PREDECESSORS | STANDARD TIME (Days) | STANDARD COST | CRASH TIME (Days) | CRASH COST |
| A | -- | 7 | $2,000 | 5 | $3,500 |
| B | A | 10 | $3,000 | 8 | $4,700 |
| C | A | 8 | $3,400 | 7 | $3,700 |
| D | C | 6 | $1,600 | 4 | $2,600 |
| E | C | 7 | $1,900 | 4 | $4,000 |
| F | D,E | 5 | $1,200 | 3 | $2,800 |
| G | B,C | 11 | $8,200 | 8 | $10,900 |
| H | F,G | 4 | $2,600 | 3 | $3,800 |