Question: Seven jobs are to be processed through a single machine. The processing times and due dates are given below. Job 1 2 3 4 5

Seven jobs are to be processed through a single
Seven jobs are to be processed through a single machine. The processing times and due dates are given below. Job 1 2 3 4 5 6 7 Processing time 3 6 8 4 2 1 7 Due date 4 8 12 15 11 25 21 Determine the sequence of the jobs in order to minimize a. mean flow time b. number of tardy jobs c. maximum lateness