Question: Shane is a project manager for software development. She is assign to develop a thesis system. Phase 1 module , time and due date as
- Shane is a project manager for software development. She is assign to develop a thesis system. Phase 1 module , time and due date as follows:
Module No
Module Name
Time in days
Due Date in days
1
Module master user
2
10
2
module master menu
3
15
3
module master thesis type
1
12
4
module master supervisor
2
17
5
module thesis student
4
30
6
module upload proposal
6
16
7
module approval proposal
3
9
8
module report type 1
2
28
9
module reminder
2
18
10
module report type 2
2
16
-
- Create a job sequencing model for this case (5 points) (LO 4)
- Find the optimal job sequencing for this case (5 points) (LO 4)
- Provide your answer with final Screen shoot showing the formula on how you find the answer of point b. (2 points) (LO 4)