Question: Sharp Manufacturing Inc. is analyzing a project with the following projected cash flows: Year Cash Flow 0 - $ 1 , 1 8 0 ,

Sharp Manufacturing Inc. is analyzing a project with the following projected cash flows:
Year
Cash Flow
0-$1,180,000
1275,000
2400,000
3480,000
4320,000
This project exhibits cash flows.
Sharps desired rate of return is 6.00%. Given the cash flows expected from the company's new project, compute the projects anticipated modified internal rate of return (MIRR).(Hint: Round all dollar amounts to the nearest whole dollar, and your final MIRR value to two decimal places.)
6.41%
7.21%
8.01%
8.81%
Sharps managers are generally conservative, and select projects based solely on the projects modified internal rate of return (MIRR). Should the companys managers accept this independent project?
No
Yes
Youve just learned that the analyst who assembled the projects projected cash flow information used incorrect data. Youve reexamined the source data and determined that the revised annual cash flow information should be:
Year
Cash Flow
0-$998,750
1275,000
2-300,000
3360,000
4240,000
Again, if Sharps desired rate of return is 6.00%, then the projects revised modified internal rate of return (MIRR) should be .(Hint: Round all dollar amounts to the nearest whole dollar, and your final MIRR value to two decimal places.)
If, again, Sharps managers continue to exhibit their general conservatism and select their investment projects based only on the projects MIRR, should they accept the project?
No
Yes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!