Question: Sheffield, Inc. began work on a $ 6 , 4 9 9 , 0 0 0 contract in 2 0 2 2 to construct an

Sheffield, Inc. began work on a $6,499,000 contract in 2022 to construct an office building. Sheffield uses the cost-recovery method. At December 31,2022, the balances in certain accounts were Construction in Process $1,757,000, Accounts Receivable $260,000, and Billings on Construction in Process $1,055,000.
Indicate how these accounts would be reported in Sheffield's December 31,2022, statement of financial position. (List assets in reverse order of liquidity.)
Sheffield, Inc.
Statement of Financial Position
December 31,2022
$
$