Question: Shirts are made in a process with two resources. The first resource has a capacity of 9.5 shirts per hour. The capacity of the second
Shirts are made in a process with two resources. The first resource has a capacity of 9.5 shirts per hour. The capacity of the second resource is 17 shirts per hour. The first resource has 10 workers and the second resource has 8 workers. What is the capacity of the process if workers can now work at both resources and processing times do not change? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. Answer is complete but not entirely correct