Question: Shirts are made in a process with two resources. The first resource has a capacity of 9.5 shirts per hour. The capacity of the second

 Shirts are made in a process with two resources. The first

Shirts are made in a process with two resources. The first resource has a capacity of 9.5 shirts per hour. The capacity of the second resource is 17 shirts per hour. The first resource has 10 workers and the second resource has 8 workers. Demand for this process is 5 shirts per hour. What is the average labor utilization (\%)? Note: Do not round intermediate calculations. Round your answer to 1 decimal place