Question: Shirts are made in a process with two sequential resources. The capacities of the resources are 9 . 5 and 1 7 shirts per hour.

Shirts are made in a process with two sequential resources. The capacities of the resources are 9.5 and 17 shirts per hour.
Instruction: Round your answer to three decimal places.
What is the capacity of this process in terms of shirts per hour?
shirts per hour