Question: Shorten the project duration by utilizing the information presented in the table below using 3 compression cycles. Evaluate the primary cost of the project and

Shorten the project duration by utilizing the information presented in the table below using 3 compression cycles. Evaluate the primary cost of the project and the cost of the project after conducting crashing.
\table[[Activity,IPA,Normal,Crash,Cost/day],[Duration,Cost,Duration,Cost],[G,-,12,1200,10,1400,100],[H,G,20,1800,15,2800,200],[I,G,40,16000,30,22000,600],[j,I,30,1400,20,2000,60],[K,J, L,50,3600,40,4800,120],[L,H,60,13500,45,18000,300]]