Question: ACTIVITY DESCRIPTION PREDECESSOR ( S ) TIME ( WEEKS ) COST ( $ ) NORMAL CRASH NORMAL CRASH A Finalize site and building contracts 7
ACTIVITY DESCRIPTION PREDECESSORS TIME WEEKS COST $
NORMAL CRASH NORMAL CRASH
A Finalize site and building contracts
B Hire production manager A
C Select local promoter A
D Target headline entertainers C
E Hire operations manager A
F Design promotional Web site C
G Set TV deal F
H Hire director G
I Plan for TV camera placement H
J Set venue capacity B
K Ticketmaster contract F J
L Target support entertainers D
M Travel accommodations for staff C
N Passes and stage credentials I, L
O Travel accommodations for talent L
P Sound and staging B
Q Secure merchandise deals C
R Onsite ticketing K
S Hire sponsor coordinator C
T Finalize sponsors S
U Defineplace signage for sponsors T X
V Hire security director E
W Develop site plan E
X Power, plumbing, AC toilet services W
Y Set policefire security plan V
Z Online merchandise sales Q
End A dummy end node PRNOZUYM At the Hard Rock Cafe, like many organizations, project management is a key planning tool.
With Hard Rocks constant growth in hotels and cafes, remodeling of existing cafes, scheduling
for Hard Rock Live concert and event venues, and planning the annual Rockfest, managers rely
on project management techniques and software to maintain schedule and budget performance.
Tomasso is in charge of the Rockfest event, which is attended by well over enthusiastic
fans. The challenge is pulling it off within a tight month planning horizon. As the event
approaches, Tomasso devotes greater energy to its activities. For the first months, Tomasso
updates his Microsoft Project charts monthly. Then at the month mark, he updates his progress
weekly. At the month mark, he checks and corrects his schedule twice a week.
Early in the project management process, Tomasso identifies major tasks called level
activities in a work breakdown structure, or WBS: talent booking, ticketing, marketingPR
online promotion, television, show production, travel, sponsorships, operations, and
merchandising. Using a WBS each of these is further divided into a series of subtasks. Table
below identifies of the major activities and subactivities, their immediate predecessors,
normal time and crash time, and normal cost and crash cost estimates.
The day of the rock concert itself is not the end of the project planning. Its nothing but
surprises. A band not being able to get to the venue because of traffic jams is a surprise, but an
anticipated surprise. We had a helicopter on standby ready to fly the band in says Tomasso.
On completion of Rockfest in July, Tomasso and his team have a month reprieve before
starting the project planning process again.
Questions
Draw AON network Please use software tool such as Excel or PowerPoint to
draw the diagram. Note, to get credit, your diagram must clearly tell from which activity to
what activity.
Perform CPM analysis by identifying ES EF LS LF Slack time, and whether critical, for
each activity.
What is the critical path? How long does the project take?
To shorten the project time to by weeks, which activity or activities should be crashed to
minimize the increased cost? What is the new project duration after crashing? What is the
increased cost? What is the critical paths now?
To further shorten the project time by week, which activity or activities should be crashed
such that the increased cost is minimal? What is the new project duration after crashing?
What is the additional cost?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock