Question: Show all setting out and working rounding all values when necessary to 2 decimal places. * Assume a lag of 7 weeks between F and
Show all setting out and working rounding all values when necessary to 2 decimal places.

* Assume a lag of 7 weeks between F and H
Use the information above to answer the following questions.
-
Construct an AON network showing the early start, early finish, late start and late finish and duration of each activity on each node.
-
Name the critical path
-
What is the project length?
-
How many paths does this project have?
-
How many nodes does this project have?
-
Which activity can be delayed the longest without affecting the critical path
-
Using the table above what is the "most likely" duration of activity G?
-
Identify the burst activity(ies) and the merge activity(ies) if any
-
Determine the project variance
-
What is the cost of completing the project in a normal time?
-
If I need to reduce the project by 4 weeks which activity(ies) should be crashed and by how much will this increase the project cost?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
