Question: (SHOW ALL WORK) Using the above precedence diagram (all task times in minutes) and a cycle time of 1.5 minutes, use the longest task time

(SHOW ALL WORK) Using the above precedence

(SHOW ALL WORK) Using the above precedence diagram (all task times in minutes) and a cycle time of 1.5 minutes, use the "longest task time" rule to:

  1. balance the line (list the tasks in order by workstation),
  2. calculate total time available,
  3. calculate total idle time, and
  4. calculate assembly-line efficiency.
F 0.4 A D 0.1 0.5 I 0.5 G 0.4 B 0.7 C 0.2 H 0.6 E 0.8