Question: show me the step and answer. Question 5 Given the optimistic estimate (to), most likely estimate (tm), and pessimistic estimate (to) in Table 4 based

show me the step and answer.
Question 5 Given the optimistic estimate (to), most likely estimate (tm), and pessimistic estimate (to) in Table 4 based on the positively skewed beta probability distribution in PERT (Project Evaluation & Review Technique). (a) Calculate i. Expected activity duration (te). (4 marks, C3) Standard deviation (de) of the expected duration. (4 marks, C3) Variance (0e)of the expected duration. (4 marks, C3) (b) The critical path is A-C-E-G = 21 days (refer to Appendix A1 and A2 - Areas under the standard normal curve) 1. Compute the probability the project will be done in 23 days. (4 marks, C3) IL Compute the probability the project will be done in 20 days. (4 marks, C3)Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
