Question: show work please A project has the following Activities, Activity times, and predecessors. Time Predecessor Activity 3 B 4 A 4 A D 14 B

show work please A project has the followingshow work please
A project has the following Activities, Activity times, and predecessors. Time Predecessor Activity 3 B 4 A 4 A D 14 B E 3 C.D Q The critical path of this project is: A A-B-C-D-E B. A-B-C CA-C-E D. A-B-D-C IB-C-E