Question: Managers are using PERT to manage their project. The project has the following Activities, Activity times, and predecessors. Activity MIN, MOST LIKELY, MAX Predecessor A
Managers are using PERT to manage their project.
The project has the following Activities, Activity times, and predecessors.
| Activity | MIN, MOST LIKELY, MAX | Predecessor |
| A | 3, 6, 12 | - |
| B | 2, 4, 6 | - |
| C | 4, 5, 9 | A |
| D | 1, 4, 4 | B |
| E | 3, 3, 3 | C,D |
The expected completion time of the project is