Question: show work PROBLEM 6-20 POINTS The following is a list of activities that must be completed in order to assemble a car. A) Draw the

show work show work PROBLEM 6-20 POINTS The following is a
PROBLEM 6-20 POINTS The following is a list of activities that must be completed in order to assemble a car. A) Draw the precedence diagram. B) Calculate the cycle time if there are 12 hours in a workday and 960 units desired per day. C) Balance the line using the longest operation time as a selection rule. D) Calculate the efficiency rating, E) How much overtime would be needed for an additional 40 units? Task Time Fea sible TASK TIME PRECEDING Station TaskTime Rem aining Tasks TASK (Seconds) TASK 15 E,F,G