Question: Show Work The following information relates to a project (task times are in weeks). Use the information to solve for the critical path and then

Show Work The following information relates to a
Show Work The following information relates to a project (task times are in weeks). Use the information to solve for the critical path and then to determine the probability that the project could be completed within 34 weeks tom 5 Task Preceding Tasks A None B A D B E F DE 3 4 2 8 1 6 G 11 7 8 7 10 10 14 13 10 Click the icon to view the table of standard normal probabilities The probability that the project is completed within 34 weeks is Eter your response rounded to four decimal places)