Question: show work Using the following project information, calculate the variance for each of the project activities. Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic

show work
show work Using the following project
show work Using the following project
Using the following project information, calculate the variance for each of the project activities. Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) Activity A 2 3 5 none B 2.5 4 4 5 A 7 8 A 3 5 7 B.C E 3 6 15 B.C F 2 8 D 0 0 0 1 - - 4 5 6 E H 6 ON 6 8 F 5 00 11 G 2 3 3 HI M1 (Round your answers to 2 decimal places, e.g. 1.75.) Activity Variance A B D E F G H 1