Question: (SHOW YOUR COMPLETE WORK) The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A
(SHOW YOUR COMPLETE WORK) The activities needed for a new project your company is undertaking are listed in the following table.
| ACTIVITY | IMMEDIATE PREDECESSOR(S) |
| A | ---- |
| B | ---- |
| C | B |
| D | A |
| E | ---- |
| F | C |
| G | D |
| H | C, E |
| I | D, E |
| J | F, H |
| K | G, I |
| L | H |
The activity times were determined for the project, and were as below.
| ACTIVITY | ACTIVITY TIME (in weeks) |
| A | 5 |
| B | 4 |
| C | 3 |
| D | 2 |
| E | 4 |
| F | 6 |
| G | 3 |
| H | 2 |
| I | 5 |
| J | 2 |
| K | 5 |
| L | 3 |
Construct the project network diagram using Activity-on-Node (AON) approach. [6 points]
Determine the earliest start (ES) time, earliest finish (EF) time, latest finish (LF) time, and latest start (LS) time for all project activities. [14 points]
Determine slack times for all project activities. [7 points]
Identify the critical path(s) in the project network. [2 points]
How long will it take to complete the entire project? [2 points]