Question: (SHOW YOUR COMPLETE WORK) The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A

(SHOW YOUR COMPLETE WORK) The activities needed for a new project your company is undertaking are listed in the following table.

ACTIVITY

IMMEDIATE PREDECESSOR(S)

A

----

B

----

C

B

D

A

E

----

F

C

G

D

H

C, E

I

D, E

J

F, H

K

G, I

L

H

The activity times were determined for the project, and were as below.

ACTIVITY

ACTIVITY TIME (in weeks)

A

5

B

4

C

3

D

2

E

4

F

6

G

3

H

2

I

5

J

2

K

5

L

3

Construct the project network diagram using Activity-on-Node (AON) approach. [6 points]

Determine the earliest start (ES) time, earliest finish (EF) time, latest finish (LF) time, and latest start (LS) time for all project activities. [14 points]

Determine slack times for all project activities. [7 points]

Identify the critical path(s) in the project network. [2 points]

How long will it take to complete the entire project? [2 points]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!