Question: SHOW YOUR WORK FOR CREDIT Cost per Equivalent UnitWeighted-Average Method Superior Micro Products uses the weighted-average method in its process costing system. Data for the
SHOW YOUR WORK FOR CREDIT
Cost per Equivalent UnitWeighted-Average Method
Superior Micro Products uses the weighted-average method in its process costing system. Data for the Assembly Department for May appear below:
|
| Materials | Labor | Overhead | |||
| Work in process, May 1 | $ | 32,000 | $ | 52,806 | $ | 257,175 |
| Cost added during May | $ | 194,125 | $ | 35,204 | $ | 171,450 |
| Equivalent units of production |
| 2,700 |
| 2,600 |
| 2,500 |
Required:
Calculate the cost per equivalent unit for materials, labor, overhead. Show each separately and in total.
Please show your answer here:
Cost per equivalent unit Materials Labor Overhead Total
$ _______ $ ______ $ ______ $ ________