Question: Shown below is a Material Requirements Planning Record for 4 weeks Week 1 2 3 4 Gross Requirements 0 0 0 528 Scheduled Receipts 0
Shown below is a Material Requirements Planning Record for 4 weeks
| Week | 1 | 2 | 3 | 4 |
| Gross Requirements | 0 | 0 | 0 | 528 |
| Scheduled Receipts | 0 | 0 | 0 | 126 |
| Proj Ending Inventory | 100 | 100 | 100 | 100 |
| Net Requirements | 0 | 0 | 0 | NR4 |
On Hand at the end of week 0:
Min Order = 1
Lead Time =1
What are the net requirements for period 4? (NR4)
Step by Step Solution
There are 3 Steps involved in it