Question: Shown below is a Material Requirements Planning Record for 7 weeks Week 1 2 3 4 5 6 7 Gross Requirements 0 0 0 500

Shown below is a Material Requirements Planning Record for 7 weeks

Week

1

2

3

4

5

6

7

Gross Requirements

0

0

0

500

400

300

0

Scheduled Receipts

0

0

0

0

0

0

0

Proj Ending Inventory

0

0

0

0

0

0

0

Net Requirements

0

0

0

500

400

300

0

Planned Receipts

0

0

0

500

400

300

0

Planned Orders

[ Select ] ["200", "300", "0", "500", "400", "100"]

[ Select ] ["200", "100", "400", "500", "0", "300"]

[ Select ] ["100", "200", "300", "0", "500", "400"]

[ Select ] ["300", "500", "0", "400", "200", "100"]

[ Select ] ["100", "0", "300", "500", "400", "200"]

[ Select ] ["100", "0", "300", "500", "400", "200"]

[ Select ] ["300", "400", "100", "0", "200", "500"]

On Hand at the end of week 0: 0

Min Order = 1

Lead Time =1

Complete the Planned Order entries for all 7 periods.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!