Question: Shown below is a Material Requirements Planning Record for 7 weeks Week 1 2 3 4 5 6 7 Gross Requirements 0 0 0 500
Shown below is a Material Requirements Planning Record for 7 weeks
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Gross Requirements | 0 | 0 | 0 | 500 | 400 | 300 | 0 |
| Scheduled Receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Proj Ending Inventory | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Net Requirements | 0 | 0 | 0 | 500 | 400 | 300 | 0 |
| Planned Receipts | 0 | 0 | 0 | 500 | 400 | 300 | 0 |
| Planned Orders | [ Select ] ["200", "300", "0", "500", "400", "100"] | [ Select ] ["200", "100", "400", "500", "0", "300"] | [ Select ] ["100", "200", "300", "0", "500", "400"] | [ Select ] ["300", "500", "0", "400", "200", "100"] | [ Select ] ["100", "0", "300", "500", "400", "200"] | [ Select ] ["100", "0", "300", "500", "400", "200"] | [ Select ] ["300", "400", "100", "0", "200", "500"] |
On Hand at the end of week 0: 0
Min Order = 1
Lead Time =1
Complete the Planned Order entries for all 7 periods.