Question: Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. (Enter your responses as integers. A response

Shown below is a partially completed MPS record

Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "O" is equivalent to being not applicable.) Item: Ball bearings Order Policy: 500 units Lead Time: 1 week Week 5 6 7 Quantity on Hand: 400 1 2 3 4 8 9 10 550 350 350 450 300 350 150 300 400 450 300 350 250 250 250 200 150 100 100 50 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity 500