Shown below is a partially completed MPS record for ball bearings 8 9 10 400 300 400 a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Ball bearings Order Policy: 500 units Lead Time: 1 week Quantity Week on Hand: 400 1 2 3 4 5 6 7 Forecast 550 350 350 500 350 350 150 Customer orders 300 350 250 200 150 100 100 (booked) Projected on-hand inventory MPS quantity 500 100 150 100 00 IC