Question: Shown below is a partially completed MPS record for hand drills. a. Develop the MPS record for the hand drills. (Enter your responses as integers.
Shown below is a partially completed MPS record for hand drills.
a. Develop the MPS record for the hand drills. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)
| Item: Hand drills | Order Policy: 60 units | |||||
| Lead Time: 1 week | ||||||
| Quantity on Hand: 30 | Week | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | |
| Forecast | 15 | 40 | 5 | 25 | 55 | 35 |
| Customer orders (booked) | 20 | 30 | 10 | 15 | 0 | 0 |
| Projected on-hand inventory |
|
|
|
|
|
|
| MPS quantity |
|
|
|
|
|
|
| MPS start |
|
|
|
|
|
|
| Available-to- promise (ATP) inventory |
|
|
|
|
|
|
b. A distributor of the hand drills places an order for
_____
units. What is the appropriate shipping date for the entire order?
The order should ship on week
nothing.
(Enter your response as an integer.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts