Shown below is a partially completed MPS record for hand drills. a. Develop the MPS record for the hand drills. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Hand drills Quantity Week on Hand: 30 1 2 3 15 40 5 Forecast Customer orders 20 25 15 (booked) Projected on-hand 10 30 15 inventory MPS quantity 0 60 0 60 0 60 MPS start Available-to- promise (ATP) inventory 4 20 20 55 60 0 Order Policy: 60 units Lead Time: 1 week 5 6 55 35 0 0 0 25 0 60 60 0 0 60