Question: Simsel is evaluating a project which has an accounting break-even point of 7.264 units. The project will require $398,000 for fixed assets which will be

 Simsel is evaluating a project which has an accounting break-even point

Simsel is evaluating a project which has an accounting break-even point of 7.264 units. The project will require $398,000 for fixed assets which will be depreciated straight-line to zero over the project's four-year life. The fixed costs are $164,800 and the projected variable cost per unit is $24.57. What is the projected sales price per unit? Multiple Choice $56.59 $58.18 $64,02 $60.95