Question: Simulation 1 - Project Management Suppose that a software development project team has arrived at the following time estimates for a software project. a .
Simulation Project Management
Suppose that a software
development project team has
arrived at the following time
estimates for a software project.
a The duration of each task is described by a normal statistical
distribution. If the duration of each task was precisely the mean of this
distribution, what would the duration of the project be
b Report the overall mean duration of the project from simulations of
the above model using the statistical distributions and SimQuickHow does this number compare with the duration reported in part a
Project duration mean inventory of EndSimulation duration