Question: Situation 1: WBS Element BCWS (PV) BCWP (EV) ACWP (AC) P $1,000 $1,100 $1,150 Q $2,000 $1,800 $2,100 R $1,000 $1,200 $1,050 S $2,000 $1,900

Situation 1:

WBS Element

BCWS (PV)

BCWP (EV)

ACWP (AC)

P

$1,000

$1,100

$1,150

Q

$2,000

$1,800

$2,100

R

$1,000

$1,200

$1,050

S

$2,000

$1,900

$1,800

Using Situation 1 above, which WBS element is behind schedule but under budget?

Element P

Element Q

Element R

Element S

Using Situation 1 above, which WBS element has a favorable cost variance of $150?

Element P

Element Q

Element R

Element S

Using Situation 1 above, the cost performance index (CPI) for WBS element R is

0.875 1.14 0.952 0.833 1.20

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!