Which of the following is a direct responsibility of the project manager?
Part 2
A.
performing all of the activities in the project
B.
drawing the network diagram
C.
making sure that the people assigned to the project receive the motivation, direction, and information needed to do their jobs
D.
calculating completion probabilities for all tasks in the projec