Which of the following is a direct responsibility of the project manager?
Part
A
performing all of the activities in the project
B
drawing the network diagram
C
making sure that the people assigned to the project receive the motivation, direction, and information needed to do their jobs
D
calculating completion probabilities for all tasks in the projec