Slipway outfitting and quay outfitting have equal and most extended process times ( 2 1 weeks each
No answer yet for this question.
Ask a Tutor
Question:
Slipway outfitting and quay outfitting have equal and most extended process times weeks each
All other stations have different process times in weeks or multiples all integers
Draw the assembly line. Show names and process times. points
Calculate the capacity of the shipyard. points
Add three parallel lines to the system to get the best capacity. Draw the new assembly line and calculate the bottleneck, cycle time and the new capacity. points
If you increase the efficiency of the new bottleneck and reduce its process time by what will be the new bottleneck, cycle time and capacity? Please draw the new assembly line and show your calculations. points