Question: slove mcq questions 17-Progress is compared against the ----------- to determine whether project is ahead of or behind the schedule A. Planning B. Earning Value

slove mcq questions

17-Progress is compared against the ----------- to determine whether project is ahead of or behind the schedule

A. Planning

B. Earning Value

C. Baseline

D. Plan Budget

Youre working on a project that has an EV of $7,362 and a PV (BCWS) of $8,232. Whats your SV?

A. - 870

B. 0.89

C. No enough information

D. 870

You are working on a project with a PV of $56,733 and an SPI of 1.2. Whats the earned value of your project?

A. 0.72

B. . $68,733

C. $47,277.50

D. $ 68079.60

-Which among the listed below does not represent as reasons for adjusting estimates?

A. Things go wrong on projects.

B. None of the given answers are correct.

C. Interaction costs are hidden in estimates.

D. Normal conditions do not apply.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!