Question: slove mcq questions 17-Progress is compared against the ----------- to determine whether project is ahead of or behind the schedule A. Planning B. Earning Value
slove mcq questions
17-Progress is compared against the ----------- to determine whether project is ahead of or behind the schedule
A. Planning
B. Earning Value
C. Baseline
D. Plan Budget
Youre working on a project that has an EV of $7,362 and a PV (BCWS) of $8,232. Whats your SV?
A. - 870
B. 0.89
C. No enough information
D. 870
You are working on a project with a PV of $56,733 and an SPI of 1.2. Whats the earned value of your project?
A. 0.72
B. . $68,733
C. $47,277.50
D. $ 68079.60
-Which among the listed below does not represent as reasons for adjusting estimates?
A. Things go wrong on projects.
B. None of the given answers are correct.
C. Interaction costs are hidden in estimates.
D. Normal conditions do not apply.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
