Question: Smith and his project team are currently breaking down all the project deliverables into the smallest useful units so that they can then estimate costs

Smith and his project team are currently breaking down all the project deliverables into the smallest useful units so that they can then estimate costs for each of these units and then aggregate these estimates into a total project cost estimate. What is the name of the technique that Sumith and his team are using to estimate costs? Parametric estimating Bottom-up estimating Low-level estimating Project management software