Question: You and your team are currently breaking down the project deliverables into the smallest useful units so you can estimate costs for each of these
You and your team are currently breaking down the project deliverables into the smallest useful units so you can estimate costs for each of these units then aggregate these cost estimates into a total project cost estimate. What is the name of the technique that you are using