Question: So total 5 workers working for whole stations. First worker working on 1 , 2 , 3 tasks, Second worker working on 4 , 5

So total 5 workers working for whole stations. First worker working on 1,2,3 tasks, Second worker working on 4,5 tasks. Third worker working on 6,7 tasks. Fourth worker working on 8th. Last 5th working workinh on 9,10,11 stations. Time is given in diagram. Now first thing we need to focus on is: For thise setup what is the cycle time?
1. Management wants to meet the demand efficiently. Use Longest processing time rule- to balance the assembly line. Start calculating number of stations ans resolving ties by selecting the task with the higher number.
2. Can the current setup meet the demand of assembling 54 products per day with three 6-hours shifts breaks?
Lastly 3. After finding a balanced assembly line setup, how can production be increased further?
 So total 5 workers working for whole stations. First worker working

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!