Question: Software Ltd has established a project team to undertake some important market research work. It is possible to reduce the expected or normal times for

Software Ltd has established a project team to undertake some important market research work. It is possible to reduce the expected or normal times for certain activities in units of one week (but not in fractions of a week) but at an extra cost. The relevant information is given below.

Activity

Predecessor

Normal Time (weeks)

Normal Cost ($)

Crash Time (weeks)

Crash Cost ($)

A

5

4000

3

6000

B

4

3000

4

3000

C

A

2

6000

1

21000

D

C

4

1000

4

1000

E

B

5

4000

3

7000

F

B

5

7000

1

14000

G

B, C

4

4000

2

24000

H

F

3

5000

2

15000

In addition to the costs shown there is a cost of retainer fees and administration overheads of $10000 for each week that the project lasts.

a) What is the normal expected duration of the project? What is the critical path?

The normal expected duration of the project is: Answer
The critical path is: Answer

b) What would be the cost of completing the project using the normal durations?

c) What would be the duration of the project if costs are to be minimized?

Activity

Maximum Crash Time (weeks)

Crash Cost/week

A

Answer

Answer

B

Answer

Answer

C

Answer

Answer

D

Answer

Answer

E

Answer

Answer

F

Answer

Answer

G

Answer

Answer

H

Answer

Answer

Stage

Crash Activity

Time Reduction (weeks)

Resulting Critical Path(s)

Project Duration (weeks)

Project Direct Costs ($)

Crash Cost ($)

Total Indirect Costs ($)

Total Project Costs ($)

0

1

2

Therefore the optimal project duration is .. weeks, and the optimal project cost is $ ..........

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!