Question: Software project management Assume you have a project with ten activities labeled A-J, as shown in Table 2 below. Table 2 Activity Preceding Duration Early

Software project management Assume you have a

Software project management

Assume you have a project with ten activities labeled A-J, as shown in Table 2 below. Table 2 Activity Preceding Duration Early Late Event Finish Finish Slack Critical Path (Y/N) A 4 B A 5 C A 6 D . 7 E A, D 6 F C, E 5 G D, E 4 H E 3 I F, G 4 J H1 5 (a) Derive the earliest completion time (EF), latest completion time (LF), and slack for each of the following task (begin at time = 0). *No need to provide drawing, just copy, paste and fill in Table 2. [10 marks]