Question: software project management Derive the earliest completion time (EF), latest completion time (LF), and slack for each of the following task (begin at time =
software project management
Derive the earliest completion time (EF), latest completion time (LF), and slack for each of the following task (begin at time = 0). Write your answer in Table 2. [10 marks]
Table 2
| Activity | Preceding Event | Duration | Early Finish | Late Finish | Slack | Critical Path (Y/N) |
| A | - | 5 |
|
|
|
|
| B | A | 15 |
|
|
|
|
| C | A | 5 |
|
|
|
|
| D | A | 10 |
|
|
|
|
| E | C, D | 15 |
|
|
|
|
| F | B, E | 5 |
|
|
|
|
| G | F | 5 |
|
|
|
|